PROJECT MANAGEMENT GROUP FOR ENERGY FACILITIES CONSTRUCTION
UNDER THE PRESIDENT OF THE REPUBLIC OF TAJIKISTAN
Tenders
REQUEST FOR EXPRESSIONS OF INTEREST (EXTENSION)
(CONSULTING SERVICES – FIRMS SELECTION)
Assignment Title: Project Management Consultant of the Rogun HPP (PMC)
Procurement Reference No. (as per Procurement Plan): SFRHPP/CS/QCBS/01
Country: Republic of Tajikistan
Project name: Sustainable Financing for Rogun Hydropower Project (P181029)
Project Implementation agency: Project Management Group under the President of the Republic of Tajikistan (Rogun PMG)
The Republic of
Thursday, 14 March 2024 10:01 1450
REQUEST FOR EXPRESSIONS OF INTEREST (EXTENSION)
(CONSULTING SERVICES – FIRMS SELECTION)
Assignment Title: Project Management Consultant of the Rogun HPP (PMC)
Procurement Reference No. (as per Procurement Plan): SFRHPP/CS/QCBS/01
Country: Republic of Tajikistan
Project name: Sustainable Financing for Rogun Hydropower Project (P181029)
Project Implementation agency: Project Management Group under the President of the Republic of Tajikistan (Rogun PMG)
The
Wednesday, 14 February 2024 18:56 1697
General Procurement Notice
Republic of Tajikistan
Construction of Rogun Hydro Power Plant Project (Lot-4 – Left Bank Structures)
Sector: Energy
Mode of Financing: IsDB Instalment Sale and Loan
Financing No. TJK1042
The Government of the Republic of Tajikistan has applied for financing in the amount of US$ 150.0 million equivalent from the Islamic Development Bank towards
Wednesday, 14 February 2024 16:54 1587
REQUEST FOR EXPRESSIONS OF INTEREST
(CONSULTING SERVICES – FIRMS SELECTION)
Assignment Title: Electricity Sector Cost of Service Study
Reference No. (as per Procurement Plan): RHPP/CS/QCBS/04
Republic of Tajikistan
Project Management Group
under the President of the Republic of Tajikistan (Rogun PMG)
Consulting services for Electricity Sector Cost of Service Study
Contract reference: RHPP/CS/QCBS/04
The Republic of Tajikistan has applied
Tuesday, 02 January 2024 11:05 1725
27 October 2023
In 2014, an Environmental and Social Impact Assessment was prepared for the Rogun Hydropower Project (HPP) on the Vakhsh River in Tajikistan and there were meetings in Almaty (Kazakhstan) and Dushanbe (Tajikistan) to discuss this ESIA and other planning documents. Documents from 2014 may be found on this
Friday, 27 October 2023 12:18 1115
REQUEST FOR QUOTATIONS
Project Management Group for Energy Facilities Construction
under the President of the Republic of Tajikistan
Technical Assistance For Financing Framework for Rogun Hydropower Project, Grant № IDA-E1460
The Government of the Republic of Tajikistan has received funding from the World Bank and the Asian Infrastructure Investment Bank (AIIB) toward the costs
Wednesday, 18 October 2023 17:06 994
REQUEST FOR EXPRESSIONS OF INTEREST
Republic of Tajikistan
Technical Assistance for Financing Framework for
Rogun Hydropower Project
Consulting services: Senior Project Translator
Project Background
The Government of the Republic of Tajikistan has received financing from the World Bank and Asian Infrastructure Investment Bank (AIIB) towards the cost of the Technical Assistance for Financing
Friday, 13 October 2023 10:52 908
REQUEST FOR EXPRESSIONS OF INTEREST (EXTENSION)
Republic of Tajikistan
Technical Assistance for Financing Framework for
Rogun Hydropower Project
Consulting services: Senior Procurement Specialist
Project Background
The Government of the Republic of Tajikistan has received financing from the World Bank in the amount of US$15,000,000 toward the cost of the Technical Assistance (TA) for Financing
Thursday, 28 September 2023 15:58 917